Learn more about the Victorian Renewable Energy Terminal
The Victorian Government has selected the Port of Hastings as the preferred site for the Victorian Renewable Energy Terminal.
This is based on attributes that make it an ideal location for developing an offshore wind assembly port:
The establishment of the Victorian Renewable Energy Terminal at the Port of Hastings will provide the critical port capacity required to achieve Victoria’s ambitious offshore wind energy targets.
The proposed Terminal’s construction methodology will involve multiple activities and stages
Construction can be divided into four phases: mobilisation, andside works at the OTRA site, dredging and reclamation, and marine works and quay wall construction.
More information on the construction methodology can be found here: https://renewableenergyterminal.com.au/construction/methodology
An animation of the proposed construction can be found here: https://youtu.be/bxpi0MNZPQ4?si=Tw1QIGg6KCElwno3
The Terminal will act as a dedicated assembly port to receive, store, assemble and transport offshore wind components.
Commercial vessels will deliver the components to the Terminal where they will be unloaded and stored. Specialised installation vessels will then receive the components and transport them to the offshore wind zones for installation.
Some components, including the towers, will be assembled at the Terminal before being loaded onto the installation vessels.
Wind at sea is stronger and more consistent when compared to land. Analysis of the wind profiles offshore from Victoria demonstrates we have some of the best offshore wind resources in the world.
For more information on the benefits of offshore wind, visit Offshore Wind Energy Victoria at: https://www.energy.vic.gov.au/renewable-energy/offshore-wind-energy
Offshore wind energy is a new and valuable addition to our energy mix and renewable energy transition. It will help us achieve our renewable energy targets, and be an important part of Victoria’s electricity future.
The first 2 gigawatts of electricity generated by offshore wind could power 1.5 million homes. The Victorian Government has a legislated offshore wind energy generation target of 9 GW by 2040.
The Victorian Planning Minister determined an Environment Effects Statement (EES) is required for the Victorian Renewable Energy Terminal in 2023.
An EES is required for a project when it is likely to have significant environmental impacts at a regional or state level that need to be examined through an integrated and transparent process, before any statutory decision can be made.
In the case of the Victorian Renewable Energy Terminal, an EES is required as the project is being built in an area of environmental significance, and must carefully consider how impacts can be managed, avoided and mitigated.
This will occur through the development of an EES.
The EES is Victoria’s most rigorous environmental assessment process.
During the preparation of the EES, PoHC has undertaken environmental investigations to understand potential impacts from the project and identify how any impacts can be avoided, minimised or managed.
A full list of environmental studies undertaken can be found here: https://renewableenergyterminal.com.au/planning/technical-studies
Construction of the Terminal is expected to take approximately 3 years and is subject to project approvals.
Port of Hastings Corporation expects to submit the project Environment Effects Statement (EES) in early 2027.
The Victorian Renewable Energy Terminal was announced in2022 and has been progressing through both State and Commonwealth approvals.
In 2025, the project was designated a “Controlled Action” by the Commonwealth Government, allowing a bilateral agreement between the State and Commonwealth Government.
In 2026, the project received $124.5 million in project funding from the State Government and is expected to submit its State Environment Effects Statement in early 2027.
Construction and operational timelines aresubject to the approvals process.